| technical | 
| input_capacity * full_load_hours * number_of_units | 
Total installed capture capacity | 
0
 | 
0
 | 
T_CO2 / year | 
| input_capacity * full_load_hours | 
Capture capacity per unit | 
4972524
 | 
4972524
 | 
T_CO2 / year | 
| full_load_hours | 
Full load hours | 
8,000
 | 
8,000
 | 
hour / year | 
| cost | 
| total_initial_investment_per(:plant) | 
Initial investment | 
570.36 M
 | 
570.36 M
 | 
EUR / unit | 
| fixed_operation_and_maintenance_costs_per(:plant) | 
Fixed operation and maintenance costs | 
26.52 M
 | 
26.52 M
 | 
EUR / unit / year | 
| variable_operation_and_maintenance_costs_per_full_load_hour | 
Variable operation and maintenance costs | 
5768
 | 
5768
 | 
EUR / full load hour | 
| wacc | 
Weighted average cost of capital | 
7.0
 | 
7.0
 | 
% | 
| other | 
| technical_lifetime | 
Economic lifetime | 
15
 | 
15
 | 
years |